How Long Does Building a Modular House Take - Stages From Signing to Delivery
Category: Technical & Quality
Published: 2026-04-03
Delivery time is one of the main advantages of modular houses over traditional construction. But "30 days" can be misleading if you don't understand exactly what that figure covers. Here are the real stages, explained step by step.
Stage 1 - Choosing the model and configuring the offer
Everything starts with discussing your needs and intended use: choose an existing model or send your own sketch, then layout, materials and fittings are agreed together. This stage can take anywhere from a few days to a few weeks, depending on how clearly the requirements are defined from the start.
Stage 2 - Contract and production scheduling
Once the offer is agreed, the contract is signed. Standard payment is split into three installments: 5% on signing, 45% before entering production, and 50% upon completion of factory work. Important: from the moment production actually begins, the house is typically ready in about 30 working days . However, depending on the current order backlog, there may be an additional 30-45 day waiting period before work actually starts on your project.
Stage 3 - Factory production
Modules are manufactured at the Premium House factory in Margineni, Bacau. Throughout production, clients receive regular photo updates, so they can follow the house taking shape. This stage covers the steel structure, insulation, interior installations, finishes and bathroom fitting.
Stage 4 - Handover and transport
After factory work is complete, the house is handed over and transport is arranged - either through Premium House's partners or your own carrier. Transport cost depends on the route, and site access (about 4 m width, 4 m clear height, for a trailer roughly 18 m long) must be checked in advance.
Stage 5 - Placement and connections
On arrival, the house is placed on the previously prepared concrete platform (based on execution dimensions provided by Premium House), then exterior connections - water, sewage, electricity, internet - are arranged by the client, on site. Interior installations are already completed at the factory.
What can affect the total timeline
The complexity of customizations requested versus a standard model
The volume of orders already in production at the time of signing
Site access conditions and platform preparation (if not ready on time, delivery may be delayed)
Obtaining necessary permits, if required by the local city hall - see our guide to permits and authorizations
For an exact timeline specific to your project, this is always communicated before signing the contract, so you know what to expect from the start.